Lift Planning Worksheet

A worksheet for thinking through a lift before it happens — load data, rigging, exclusion zones, who signals, and what happens if the load swings. Most crush injuries under suspended loads come down to somebody standing where nobody planned for them to be.

How to use it. Work through it with the crew before the lift, not at a desk afterwards. Every blank is a decision someone would otherwise make under time pressure with a load in the air.
To print: Click "Print" below → select Portrait orientation → enable Background graphics in print settings → Print.
To fill in: Print and complete by hand, or use your browser's "Save as PDF" and fill the fields in any PDF editor.
Want help building your hoisting and rigging program?
HSE Advisor Canada is CRSP Certified, COR & ISO 45001 Lead Auditors. We will review what you have written, confirm it lines up with the requirements in your province, and help you close the gaps. The first conversation is free.

Want our most-requested checklists by email?

This resource is free to read, print and use right here — no sign-up. We can also email you our most-requested free checklists and templates. The full library is always at Free HSE Resources.

We send occasional Canadian OHS updates. Unsubscribe any time.

Lift Planning Worksheet

Planning aid · Complete before every non-routine lift
HSE ADVISOR CANADA
hseadvisor.ca
Company:
Project / site:
Prepared by:
Position:
Date:
Planned lift time:
0. Does this lift need more than this worksheet?
  • Load is at or near the equipment’s rated capacity
  • Two or more machines lifting the same load
  • Load is of unknown weight, or the centre of gravity is uncertain
  • Personnel to be lifted or suspended
  • Lifting over occupied areas, live process, public roadway or another trade
  • Blind lift — the operator cannot see the load or the landing area
  • Custom or engineered lifting device, or a load with no designed lifting points
If you ticked any box above, stop. This worksheet is not sufficient. That lift needs a plan prepared by a competent person — and where the load, rigging design or structure demands it, a professional engineer. Use this sheet only as input to that plan.
1. The load

Description:

Weight (verified how?):
Dimensions:
Centre of gravity:
Designed lifting points:
Rigging weight:
Total gross load:
Weight must be verified, not estimated from memory. Record the source — nameplate, shipping document, drawing or scale. "Looks about a tonne" is how loads get dropped.
2. The equipment
Lifting equipment:
Rated capacity at radius:
Working radius:
Boom length / configuration:
Load chart consulted:
Percentage of capacity:
RequirementWhat good looks likeY / N / N-AEvidence or gap
Capacity plate legible and currentRating posted on the machine and matched to the configuration in use.
Annual and periodic inspection currentDocumented and available on site.
Pre-use inspection completedThis shift, by the operator, recorded.
Operator competent for this machineTrained and, where required, certified for this equipment and configuration.
Load-limiting devices functionalAnti-two-block, load moment indicator or equivalent, tested.
3. Rigging
ItemSize / typeWLLSling angleInspected byCondition
RequirementWhat good looks likeY / N / N-AEvidence or gap
Rigging rated for the gross loadIncluding the effect of sling angle on tension.
Sling angle accounted forTension rises sharply as the angle from horizontal decreases.
Inspected before this liftSlings, shackles, hooks and hardware inspected and removed from service if damaged.
Edge protection fittedSofteners where slings pass over corners.
Hooks have functioning latchesAnd the load is seated in the bowl, not the tip.
Tag lines fittedLong enough to control the load without the handler entering the swing zone.
4. The swing zone — where people get crushed
RequirementWhat good looks likeY / N / N-AEvidence or gap
Exclusion zone definedA marked area covering the full swing radius, not just directly under the load.
Exclusion zone physically markedCones, tape or barriers on the ground, briefed to everyone on site.
Nobody under the load, everNo task requires a person beneath a suspended load. If one seems to, redesign the lift.
Load control methodTag lines handled from outside the swing zone.
Pinch points identifiedWhere the load could trap someone against a structure, vehicle or stack.
Landing area preparedCribbing, dunnage and a stable surface ready before the load leaves the ground.
Other trades cleared or protectedAdjacent work stopped, diverted or barriered.
A suspended load swings, and it swings further than people expect. The exclusion zone is the swing radius plus a margin, not the footprint of the load. Wind, a snatched pick or a shifting centre of gravity all widen it.

Exclusion zone dimensions and how it is marked:

5. Communication and roles
Operator:
Signal person:
Rigger:
Lift supervisor:
Spotter(s):
Signal method:
  • One designated signal person, agreed before the lift
  • Signal method agreed and understood — hand signals or radio on a confirmed channel
  • Everyone knows that anyone may signal stop
  • Radio checked and a backup arranged if the primary fails
  • Line of sight confirmed, or a relay signal person positioned
6. Ground and environment
RequirementWhat good looks likeY / N / N-AEvidence or gap
Ground bearing adequateAssessed for the machine and outrigger loads; mats or pads as required.
Outriggers fully deployedOn firm level ground with pads correctly sized.
Underground services checkedUtility locate completed where outriggers or tracks bear.
Overhead powerlines identifiedMinimum approach distance established and physically respected.
Wind within limitsManufacturer wind limit known, current wind measured, and a stop threshold agreed.
Weather and light adequateVisibility, precipitation and temperature considered.
7. Pre-lift briefing and sign-off

Everyone involved attends the briefing and signs. Anyone who arrives late is briefed before entering the area.

Name (print)RoleSignatureTime

Stop-work triggers agreed:

Lift Planning Worksheet · HSE Advisor Canada · Free to use and adapt.
hseadvisor.ca · (647) 620-5278

This is a planning aid, not a certified lift plan and not an engineered design. Critical, complex and multi-crane lifts require a plan prepared by a competent person, and in many cases a professional engineer. Confirm the requirements that apply to your jurisdiction, your equipment and your load before lifting.